Lambert Airport, Lindbergh Tunnel

Location: St. Louis, MO

Date: December 2003 - Summer 2004

Owner: St. Louis Airport Authority

Architect: URS Corporation

Contractor: McCarthy Building Companies

click to enlarge

Ready Mix Supplier: Metro Materials

PreCast Supplier: St. Louis Prestress

GRT Products:
- PC- 1000 - Mid-Range water reducer
- Polychem VR - Air Entraining Agent
- Melchem - Superplasticizer
- Super Set - Non-chloride Accelerator
- Polychem CI - Corrosion Inhibitor

Project Facts:

click to enlarge

The Lindbergh Tunnel Project is noteworthy in many respects. It is one of the largest civil projects ever undertaken by the state of Missouri, as well as one of the most expensive transportation projects per square foot ever designed in the Midwest. This is due to the sophisticated demands placed on the structure which must absorb the impact of a 1.25 million pound commercial aircraft landing directly upon it.

The tunnel utilized over 60,000 cubic yards poured in-place concrete w/ a large quantity of Architectural Concrete. As well as 680 pre-cast/pre-stressed concrete roof panels weighing 42,000 lbs. each.



Photos courtesy of Lambert St. Louis International Airport



back



General Resource Technology
2978 Center Court - Eagan, MN 55121
Phone: 800-324-8154
Fax: 651-454-4252
©2010 General Resource Technology - All rights reserved.