Pinnacle Casino
Location: St. Louis, MO
Construction Date: 2006-2007
Architect: Hellmuth, Obata + Kassabaum, Inc (HOK)
General Contractor: McCarthy Building Companies
Concrete Contractor: Vee-Jay Cement
Ready Mix Supplier: Metro Materials
GRT Products Used:
- Polychem AE: Air Entraining agent
- KB-1000: Water Reducer/Finishing Aid
- Super Set: Non-Chloride Accelerator
- MCI 2005 NS: Migrating Corrosion Inhibitor
Project Description: On the banks of the Mississippi, in the shadow of the famed Gateway Arch in St. Louis, MO the $350 million Pinnacle hotel, casino, parking garage and retail area was constructed. The schedule required high performance concrete throughout the project. The mixes varied from post tension parking decks, architectural finished form work to high strength columns and foundations. GRT's chemical admixtures were used throughout the project to provide the necessary concrete performance needed during the cold winter conditions to the hot summer conditions in St. Louis.
|